Gardex was engaged to deliver a comprehensive fencing and access solution for the construction of the new Henley Brook Primary School. Working in accordance with Department of Education specifications, the project incorporated multiple fencing systems across the site, providing security, safety, and architectural integration throughout the school grounds.
Supply & install:
- 739 linear metres of 2100mm-high hot dip galvanised garrison fencing.
- Installation of associated vehicle and pedestrian access gates.
- Supply and installation of black powder-coated chainwire fencing to sports court areas.
- Construction of a dedicated cricket net enclosure.
- Installation of multiple chainwire fencing sections at varying heights across the site.
- Supply and installation of aluminium slat fencing to selected service and screening areas.
- Installation of fall protection balustrading for elevated and pedestrian-access areas.